Module 5 · Project Management Fundamentals
Schedule risk and simulation
Replace a single opening date with a probability, by simulating the project thousands of times with each task's three-point estimate, and use the result to set honest dates and buffers.
About 25 minutes
Open in ColabEvery example as a notebook you can run, edit and save to your Google Drive.
The problem
The sponsor asked: "Will we open by 30 September?" The plan says 11 September with most likely durations, and later with PERT. Both are single dates. Neither answers the real question, which is about chance: how likely is it that everything that matters goes well enough?
The concept
Monte Carlo simulation
- For each task, draw a random duration from its range (here, a triangular distribution between optimistic and pessimistic, peaking at most likely).
- Schedule the project with those durations and record the end date.
- Repeat thousands of times.
- The results form a distribution of end dates: you can read off the probability of meeting any date.
Merge bias
When several paths join (training waits for hiring and system testing), the task starts when the slowest finishes. Each path alone might be on time, but the chance that all of them are is lower. That's why simulation usually shows later dates than adding up one path's estimates.
Using the results
- Quote dates with confidence: "P80" is the date you have an 80% chance of meeting.
- A schedule buffer is the gap between the plan's date and the date you commit to.
Example
Simulate the project 10,000 times. The random generator has a fixed seed so your numbers match these:
Edit the code and press Run (Ctrl + Enter). Examples on this page share their variables, like cells in a notebook.
Output
Deadline is working day 88
Chance of opening by 30 September: 64%
Chance of opening by 11 September (the most likely plan): 3%
P50: day 86, 2026-09-28
P80: day 92, 2026-10-06
P90: day 95, 2026-10-09The most likely plan's date had almost no chance of being met. The 30 September deadline is roughly a two-in-three chance before anything has even gone wrong. Which tasks drive the risk? Count how often each task was on the longest path:
Edit the code and press Run (Ctrl + Enter). Examples on this page share their variables, like cells in a notebook.
Output
task_id
A1 1.00
A2 1.00
F3 1.00
F2 1.00
A3 0.99
B2 0.99
C5 0.99
C3 0.99
D3 0.85
E2 0.15The planned critical path is the longest path in almost every run. The interesting split is at the end: staff training (D3) is on the longest path about 85% of the time, but in the other runs it's stocking the opening inventory (E2) that the trial run waits for. Racking and hiring almost never decide the date. So the project manager's attention belongs on permits, fit-out, network and system testing, and both training and stocking.
Walkthrough
- Run the cells. What's the P80 date? Would you tell the sponsor that, or 30 September?
- Make the permits certain (O = M = P = 15) and rerun. How much does the chance improve?
- What would cutting the fit-out's pessimistic estimate to 30 days do?
- Write the answer to the sponsor (the task below).
Practice
Practice
In the simulation, what's the chance of opening by 30 September? As a percentage, whole number.
Task
5 minAnswer the sponsor's question "Will we open by 30 September?" in 50 to 120 words: give the probability, a date you're 80% confident in, why the most likely plan's date is misleading, and one action that would improve the odds.
Your work is checked for
- A probability as a percentage
- An 80% or P80 date
- Explains why most likely is misleading
- An action (permits, fit-out, buffer, contractor)
- Between 50 and 120 words
Check your understanding
Answer every question to check.