Module 4 · Project Management Fundamentals
Scheduling and the critical path
Turn tasks and dependencies into a schedule with the critical path method (forward and backward passes, float), find the tasks that decide the opening date, and convert working days into calendar dates.
About 25 minutes
Open in ColabEvery example as a notebook you can run, edit and save to your Google Drive.
The problem
Twenty-three tasks, each with an owner pushing to finish theirs. But they don't all matter equally for the opening date. Hiring staff can slip by weeks without delaying anything; one day lost on the permits delays the whole launch by a day. Knowing which is which tells the project manager where to spend attention.
The concept
The critical path method (CPM)
- Forward pass: each task's earliest start is the latest finish of everything it depends on; earliest finish = earliest start + duration. The project's length is the last earliest finish.
- Backward pass: working back from the end, each task's latest finish is the earliest latest start of the tasks that depend on it.
- Float (slack) = latest start − earliest start: how long a task can slip without delaying the end.
- The critical path is the chain of tasks with zero float. Any delay on it delays the project.
Dates
Durations are working days. Convert with a working calendar (Monday to Friday here; real plans also remove public holidays).
Example
A scheduling function you'll reuse in later lessons:
Edit the code and press Run (Ctrl + Enter). Examples on this page share their variables, like cells in a notebook.
Output
Project length: 75 working days, opening on 2026-09-11
Critical path: A1 -> A2 -> A3 -> B2 -> C3 -> C5 -> D3 -> F2 -> F3Nine of the 23 tasks are critical. The path runs from the charter through the lease, permits and fit-out, then the network, system testing, training, the trial run and the opening. Now the tasks with the most float:
Edit the code and press Run (Ctrl + Enter). Examples on this page share their variables, like cells in a notebook.
Output
es ef ls lf float
C4 10 20 48 58 38
C1 3 10 41 48 38
E3 21 31 59 69 38
E1 13 21 51 59 38
C2 10 20 48 58 38Choosing and configuring the warehouse system, buying equipment, agreeing supplier deliveries and setting up routes can each slip by 38 working days without moving the opening. Meanwhile the permits, the fit-out and the network and system testing have none. The plan says the depot opens on 11 September, comfortably before the 30 September deadline. But this plan uses most likely durations everywhere. Redo it with the PERT expected durations:
Edit the code and press Run (Ctrl + Enter). Examples on this page share their variables, like cells in a notebook.
Output
With expected durations: 80.3 working days, opening on 2026-09-21The opening moves later, and the deadline gets closer. Lesson 5 asks the better question: what's the chance of opening by 30 September?
Walkthrough
- Run the cells. Change the permits (A3) to 20 days. What happens to the opening date?
- Change hiring the manager (D1) to 30 days. Does the opening move? Why not?
- Draw the critical path as boxes and arrows.
- Explain float to the HR lead (the task below).
Practice
Practice
How many working days of float does E3 (delivery routes) have in the most likely plan?
Task
5 minThe HR lead wants to know whether hiring can be done more slowly to save effort. Write a short reply (40 to 100 words) explaining float for D1 and D2 with the number of days, what happens if hiring slips beyond that, and what you'd ask them to do.
Your work is checked for
- Mentions float or slack
- Gives a number of days
- Says what happens beyond the float (delay, opening, critical)
- Makes a request
- Between 40 and 100 words
Check your understanding
Answer every question to check.